Equipment Installation and Commissioning: Chentai Intelligent Equipment Standard Delivery Process

Equipment delivery does not mean placing the machine on its foundation and calling it done. Chentai’s standard process is: unpacking acceptance → foundation verification → positioning and alignment → individual commissioning → integrated trial run → trial production with actual feed material → training and handover. Each stage has acceptance records to prevent problems from accumulating and only emerging at production start-up.

Seven stages

  1. Unpacking acceptance: Verify the model, accompanying documents, exterior condition, and spare parts list, and take photographs on site for the record.
  2. Foundation verification: Check the positions, elevations, and embedded components of anchor bolts against the foundation drawings, and proceed with positioning only if all deviations are within the permitted range.
  3. Positioning and alignment: Lift and position the equipment, tighten the anchor bolts, and align the longitudinal and transverse centerlines and verticality. For crushers, verify discharge outlet alignment again.
  4. Individual commissioning: First perform unloaded jogging, rotation direction, and lubrication checks, then increase the load step by step.
  5. Integrated trial run: Conduct integrated commissioning of the complete feeding—crushing—screening—conveying line to verify process coordination and anti-bridging design.
  6. Trial production with actual feed material: Run the equipment with actual material to calibrate capacity, finished-product gradation, and current parameters, and prepare commissioning records.
  7. Training and handover: Provide operation and maintenance training, hand over spare parts and accompanying documents, and explain the handling of common faults.

Customer cooperation requirements

Required: qualified foundations and anchor bolts, lifting access routes and space, a power supply and control cabinet location, raw materials for trial production, and qualified operating and electrical personnel to support the integrated trial run.

Areas most prone to problems at each stage

Stage Common issues Preventive measures
Unpacking acceptance Missing parts, mismatched accompanying parts, and undetected deformation Check the model and list against the delivered items on site during unpacking and retain photographs; record missing parts immediately
Foundation verification Deviations in anchor bolt positions and missing embedded components Complete verification before positioning the equipment and compare each item against the foundation drawings
Positioning and alignment Centerline deviation, excessive deviation from verticality, and crusher discharge outlet misalignment Use laser instruments or feeler gauges for actual measurements and retain records rather than relying on visual inspection
Individual commissioning Insufficient lubrication, incorrect rotation direction, and loose fasteners Confirm rotation direction through unloaded jogging and retighten the fasteners
Integrated trial run Transfer section blockage, mismatched material flow, or false triggering of protective devices Verify feeding section by section; do not load the entire line at once
Trial production with actual feed material Overcurrent, deviation in finished product gradation, or abnormal vibration and temperature rise Increase loading gradually from a low load, record current, vibration and temperature rise, and compare them with rated values

Which phases make up the construction period

On-site installation and commissioning usually take little time. The three phases that actually consume the most time across the entire line are:Design confirmation(the owner’s review and confirmation period for the process and specifications),Long-lead equipment procurement(motors, reducers, conveying systems, etc., which often have longer lead times than on-site construction), andCivil works and steel structures(including curing and lifting windows). Recording the start and end dates of these three phases in the schedule is more effective at preventing disputes than merely specifying “X days for installation and commissioning.”